Suppose together we visit a construction site .
The RCC slab at the 4th floor is ready for casting tomorrow.
What questions come to your mind ?
1.What kind of materials in what quantity are required for concreting of this slab ?
2.How much time shall be needed to cast this slab ?
3.What are the checks to be done before & during the slab casting ?
Let us see how do we solve these questions one by one.
We already know that:
We already know that the Nominal Mix for Grade M20 concrete is (1+1.5+3).
:
For 1 CuM of concrete , the material consumption is as follows:
Sand: {1.52/(1+1.5+3)}X 1.5 = 0.415 CuM
Aggregate: {1.52/(1+1.5+3)}. X 3 = 0.830 CuM
The time taken for casting can be derived as follows:
1.Assuming that each batch is mixed for exactly 1 minute ,then in one hour we can mix concrete using 60 bags of cement.
3.Steps for finding the duration:
3.1.Find out cement to be used.
3.2 Decide no of mixers to be deployed.
3.3 Concreting duration:
(No of cement bags/60)(1/No of mixers).
3.What are the checks to be done before the casting is taken up ?
Checks prior to casting:
1.Materials:
Availability of all materials of approved quality in adequate quantity with reasonable lead from the point of mixing.
2.Centering:
2.1 Centering plates to be at required level as per drawing.
2.2All gaps properly closed with either wooden planks, GI strips or Masking tape.
2.3.Iron clamps for the Beam & Slab sides.
3.Reinforcement:
3.1.Cover blocks in position for slab ( 15 mm ) & beams ( 25 mm).
3.2.Chairs in position for the bent up bars.
3.3.Laps of adequate length
( Slab : 60 X bar dia )
3.4. Recording of reinforcements
Thank you Shrikant
LikeLike
going grate sir
LikeLike